BID NO. 05-142 | ||||
WEST PASCO REUSE METERING AND CONTROLS PROJECT | ||||
SEPTEMBER 13, 2005 | ||||
RTD CONSTRUCTION, INC. | COGBURN BROS, INC. | TLC DIVERSIFIED, INC. | ||
ZEPHYRHILLS, FL | JACKSONVILLE, FL | PALMETTO,FL | ||
TOTAL BASE BID | $2,794,576.00 | $3,331,100.00 | $2,748,310.00 | |
ALTERNATE A.1 | $35,230.00 | $60,000.00 | $36,780.00 | |
ALTERNATE A.2 | $48,486.00 | $95,000.00 | $50,480.00 | |
ALTERNATE A.3 | $66,719.00 | $141,000.00 | $67,340.00 | |
ALTERNATE A.4 | $69,837.00 | $36,000.00 | $68,440.00 | |
ALTERNATE A.5 | $44,931.00 | $8,200.00 | $55,100.00 | |
ALTERNATE A.6 | $35,819.00 | $23,000.00 | $36,900.00 | |
ALTERNATE A.7 | $33,027.00 | $12,000.00 | $34,240.00 | |
ALTERNATE A.8 | $25,244.00 | $5,600.00 | $23,540.00 | |
ALTERNATE A.9 | $34,635.00 | $34,000.00 | $29,810.00 | |
ALTERNATE A.10 | $31,601.00 | $31,000.00 | $27,870.00 | |
*UNOFFICIAL AS READ | ||||