BID NO. 06-031F | ||||||||||||
INDUSTRIAL COATING | ||||||||||||
( PAINTING ) | ||||||||||||
FEBRUARY 6, 2006 | ||||||||||||
PAINT IT PLUS, INC. | VIKTOR CONST. CORP. | NICK'S PAINTING | HARRY'S PAINTING & ENT., INC. | M.B.E. INC. OF FL | SOURINI PAINTING, INC. | BULWARK CONST. SVS., INC. | OLYMPIC PAINTING CONTRACTING INC. | GEMINI, INC. | WEST FLORIDA MAINT., INC. | |||
WESLEY CHAPEL, FL | TARPON SPRINGS, FL | PITTSBURG, PA | NEW PORT RICHEY, FL | HOLIDAY, FL | CLEARWATER, FL | HEWITT, NJ | HOLIDAY, FL | PALM HARBOR, FL | APOLLO BEACH, FL | |||
ITEM 1. ( 1 EA ) | ||||||||||||
LUMP-SUM PRICE | $43,560.00 | $18,900.00 | $19,800.00 | $33,088.00 | $58,700.00 | $37,710.00 | $46,655.00 | $39,782.26 | $28,000.00 | $17,850.00 | ||
(WESLEY CENTER | ||||||||||||
WWTP ) | ||||||||||||
START | 10 DAYS | 14 DAYS | 7 DAYS | 15 DAYS | 14 DAYS | 21 DAYS | 14 DAYS | 7 DAYS | 30 DAYS | 15 DAYS | ||
COMPLETE | 60 DAYS | 30 DAYS | 30 DAYS | 45 DAYS | 21 DAYS | 90 DAYS | 45 DAYS | 30 DAYS | 45 DAYS | 60 DAYS | ||