BID NO. 06-120D | |||||||||||
CLEARING AND GRUBBING SERVICES | |||||||||||
JULY 6, 2006 | |||||||||||
E.L. TREVENA INC. | CROSS ENVIRO. SERVICES, INC. | E.R.G. ENT., L.L.C. | BIO-MASS TECH., INC. | CONSOLIDATED RESOURCE RECOVERY, INC. | STORM RECONSTRUCTION SERVICES, INC. | PAW MATERIALS, INC. | WAL DEN GREENE DEVELOPERS, INC. | ||||
PINELLAS PARK, FL | CRYSTAL SPRINGS, FL | BAYONET POINT, FL | LAND O' LAKES, FL | SARASOTA, FL | TUSCALOOSA, AL | BAYONET POINT, FL | WESLEY CHAPEL, FL | ||||
ITEM 1. | |||||||||||
LUMP SUM TOTAL | $268,854.00 | $253,141.25 | $183,287.00 | $132,000.00 | $97,500.00 | $124,000.00 | $263,460.00 | $373,373.73 | |||
ITEM 2. ALTERNATE BID | |||||||||||
LUMP SUM TOTAL | $163,759.50 | $186,578.75 | $67,725.00 | $19,450.00 | N/B | N/B | $113,460.00 | $186,186.86 | |||
START | 15 DAYS | 5 DAYS | 15 DAYS | 5 DAYS | 10 DAYS | 24 HOURS | 9 DAYS | 10 DAYS | |||
COMPLETION | 45 DAYS | 40 DAYS | 45 DAYS | 45 DAYS | 30 DAYS | 30 DAYS | 30 DAYS | 45 DAYS |